Published:
Case Study Stats TEST
Work Type:
Office Fit Out
Project Length:
3 months
Project Value:
£860,000
Tesco is a multi-billion pound company and is one of the most well known supermarkets in the UK. RSR was approached based on our success of a previous successful project, of similar size and scope.
We designed and installed the electrical elements necessary to get a tower operational for the garment storage that was brought in from another site and this was all done to a strict, fixed handover date.
The team worked around a number of co-ordination difficulties due to the number of services on site and restricted height issues, and were avoided by excellent project management and technical support.
Scope of works
Design, Supply and Installation of the following:
- Mains distribution
- 400amp 6way MCCB panel board to feed the new tower
- Sub-Main Cabling and alterations to the client’s existing panel board
- Digital Metering upgrade
- Split Metered Distribution Boards on each level to supply power & lighting
- Busbar system to feed lighting aisles and circulation areas
- LED lighting installation c/w sensor controls & emergency key switching
- Containment infrastructure for ELV / LV cabling
- Power for managers & charging stations
- Mechanical Conveyance control panel supplies