Case Study Stats TEST

Work Type:
Office Fit Out
Project Length:
8 weeks
Project Value:
Multi-million

RSR was chosen by E-Commerce giant – Bromley-By-Bow to design and install multiple rooms, mezzanine levels, refrigeration plant, lifts, fire alarm system and a bakery. The project was delivered within budget, to programme and with minimum impact on live operation. E-Commerce giant – Bromley-By-Bow has worked with RSR on multiple occasions and continues to see impressive results.

Scope of works

Design, Supply and Installation of the following:

  • Act as designer and principal contractor on project
  • Responsible for health and safety for project
  • Design and install 12000 sqm mezzanine
  • Installation of 4600 sqm cold room and refrigeration plant
  • Sprinkler system throughout the warehouse
  • Installed 4 goods lifts
  • HV upgrade including generator, transformer and 1.2 miles of HV cable laid
  • Insulated floor with none slip, cold resistant vinyl flooring to cold rooms
  • Lighting
  • Suspended ceilings
  • Fire alarm system throughout
  • Bakery & fish processing plant as part of fit out
  • HVAC throughout warehouse
  • Fit out of operations office, canteen and meeting suite
  • Deliver project within 40 weeks with minimum impact to site operations